Progress

Peachtree Hills Place Construction Update November 2018

Construction Update: November 2018

Site – Final connections of the major site, sewer, water and storm have been completed, and the sidewalks along Virginia and Peachtree Hills have been started on Tract III. Fire, water, and domestic water have been completed on site in all locations, and the …

Read More

Peachtree Hills Place Construction Update September 2018

Construction Update: September 2018

Site –The sidewalk along Virginia Ave. and the petanque course has been opened to the public. Site work is ongoing at Tract III, retaining ponds have been installed and soil removal will begin in the coming weeks. Additionally, water and storm tie-ins will …

Read More

PHP August 2018 Construction Update

Construction Update: August 2018

 Site – The sidewalk along Peachtree Hills Ave has been completed and re-opened to the public, by the end of the month the sidewalk along Virginia Ave. and the petanque course will be opened. Site work has begun at Tract III, tree removal …

Read More

Construction Updates: July 2018

Site – Curb work along Virginia and Peachtree Hills Ave. has been completed, along with the sidewalks. The corner at Peachtree Hills and Virginia will be completed in the coming month. The stonework on the dog park site wall, and along Virginia Ave. …

Read More

Construction Updates: June 2018

Site – All initial paving has been completed south of Austin Walk II and in the loading dock. The storm connection has been completed at the retaining pond, and work will begin next month on the dog park. Site water and fire water …

Read More

Construction Updates: May 2018

Site – Paving has begun at the road and parking lot south of Austin Walk II, and will be completed at the loading dock in the coming weeks. The old sidewalk along Peachtree Hills Ave has been removed, and the permanent sidewalk has …

Read More

Construction Updates: April 2018

Site – Underground bio detention Pond C has been completed, and the footings for the wall at detention Pond A have been started. Water meter install has begun, while underground water and sewer onsite continue. Backfill at the Clubhouse retaining wall continues, and …

Read More

Construction Updates: March 2018

Site – The Pond A wall is complete, and the crews have moved on to begin site walls at Terraces, and the Club House. Water meter install is complete, while underground water and sewer onsite continue. Excavation of Austin Walk III has begun, and …

Read More

Construction Updates: February 2018

Site – Underground bio-detention ponds A has been completed, Pond C is progressing. The modular block wall on the south side of the site has been completed. Site utilities is continuing, and water meters will begin install by the end of the month. …

Read More