Site – The sidewalk along Peachtree Hills Ave has been completed and re-opened to the public, by the end of the month the sidewalk along Virginia Ave. and the petanque course will be opened. Site work has begun at Tract III, tree removal and initial grading will continue into the coming weeks. Grading is progressing at the Terraces building and has been completed at Austin Walk 4.
Clubhouse/Lodge – The Clubhouse Post Tension slab has been poured to the entry foyer and will be completed through the offices by the end of the month. The slab on grade at the Ballroom has been completed, and the structural steel has begun. In the coming month structural steel will be completed, and the first of the hollow core slabs will be set on the second floor.
Pool Building – The glu-lam structure has been completed, and the roof timber has been installed. Protective roofing has been installed, and fire sprinkler has been completed. Going forward in-fill walls will be completed, and store front windows will be installed. In the coming month the exterior stone work will begin at the pool building.
Austin Walk I – Infill framing has been completed on the first floor, and structural framing has been completed on the third floor. The fourth-floor hollow core slabs have begun installation and will be complete by the end of the month with the topping slab. Next month we will complete another level of precast decking and begin the structural walls for the fourth-floor. Electrical, plumbing and HVAC will also begin on the third floor.
Austin Walk II – Structural metal studs have been completed in the second floor of the building, and the third-floor structural hollow core decking has been installed. By the end of the month the third-floor structural walls will be completed, and ready for structural hollow core to be set. Blocking and framing has continued in the parking level and has started on the second floor. Next month we will begin setting the pre-cast concrete decking for the third floor and pour the topping slab at this elevation.
Austin Walk IV – Footing installation continues, along with the foundation walls and columns. Underground plumbing and electrical are ongoing and will continue into the following month.