Site – The hardscapes at the Peachtree Hills entrance and around the clubhouse and pool have begun and will be ongoing for the coming months. The permanent power transformers, and power routing are beginning along with site wide natural gas in the coming months. Excavation and site prep for Austin Walk 3 and 5 has begun, and deep foundations are scheduled to begin in April.
Clubhouse/Lodge – Structural CFS has been completed and the roof structure is complete for the clubhouse, roofing has begun, and HVAC units have been flown to the lodge roof. Interior light gauge framing has been completed up to the third floor, and mechanical rough-in and windows have been completed on the lodge second floor. Exterior sheathing is ongoing, and stone is scheduled to begin in the coming months.
Pool Building – Exterior framing and the overhang structure are complete, and stone work is ongoing. Storefront windows are complete, and the pool and spa have been excavated. Concrete work of the pool will be completed in the coming month, and then the lights and painting will be completed prior to completion and filling of the pool.
Austin Walk I – Shingles have been completed on Austin Walk I, and the HVAC units have been set on the roof. Electrical, plumbing and HVAC rough-in have been completed up to the fourth floor, and drywall finishing is ongoing on the first
floor; second floor drywall hanging has begun and will continue up the building in the coming months. Mechanical rough ins have progressed on to the
fourth floor with units set in the closets up to the second floor. Exterior sheathing has been completed, and windows have been installed on all floors. The stone finish is ongoing, and stucco has begun on the north elevation.
Austin Walk II – Structural metal trusses are complete, and roofing
is scheduled to be completed in the coming weeks. Infill framing has been completed on the fourth floor and mechanical rough-in is nearing completion on the second floor. Exterior sheathing is complete along with windows up to the fourth floor. Exterior stone work has begun and will be ongoing for the coming month.
Austin Walk IV – The third floor of precast concrete decking has been completed, and the structural CFS walls for the third floor are scheduled to begin in the coming month. Infill light gauge framing on the first floor has been completed, and the mechanical rough-ins have begun. In the coming month the final floor of hollow core will be set, and light gauge framing will continue following the removal of hollow core bracing.