Construction Update: March 2019

 

Site – The hardscapes at the Peachtree Hills entrance and around the clubhouse and pool have begun and will be ongoing for the coming months. The permanent power transformers and power routing are beginning along with site-wide natural gas in the coming months. Excavation and site prep for Austin Walk 3 and 5 has begun.

Clubhouse/Lodge – Structural CFS has been completed and the roof structure is complete for the Clubhouse, shingle roofing has begun, and HVAC units have been flown to the Lodge roof. Interior light gauge framing has been complete up to the third floor, and mechanical rough-in and windows have been completed on the lodge second floor. Exterior sheathing is ongoing, and stone and stucco have begun and will continue in the coming months.

Pool Building – Exterior framing and the overhang structure are complete and stonework is ongoing. Storefront windows are complete, and the pool and spa have been excavated. Concrete work of the pool is ongoing. The lights and painting will be completed prior to completion and filling of the pool.

Austin Walk I – Electrical, plumbing and HVAC rough in have been completed up to the 4th floor, and drywall finishing is ongoing on the 1st floor, second-floor drywall hanging has begun with prime and paint to follow up the building in the coming months. Cabinet installation to start on the 1st floor and move up the building. Unit tile has begun on the 1st floor. Mechanical rough-ins have progressed on to the fourth floor with units set in the closets up to the second floor. The stone is ongoing, and stucco final coat has begun on the north elevation.

Austin Walk II –Roofing is ongoing. Infill framing has been completed on the fourth floor and mechanical rough-in is nearing completion on the second floor. Exterior sheathing is complete along with windows up to the fourth floor. Exterior stonework has begun and will be ongoing for the coming month. Plumbing, Electrical and Mechanical rough-in have started working through the building starting on the 1st floor.

Austin Walk IV – The fourth floor of precast concrete decking has been completed, and the structural load bearing walls for the 4th floor are scheduled to begin the coming month. Infill light gauge framing on the 1st through 2nd floor has been completed, and the Mechanical and Plumbing rough-ins have begun. In the coming month the Trusses and roofing will begin, and light gauge framing will continue on the 3rd floor, following the removal of hollow core bracing.

Leave a Reply

Your email address will not be published. Required fields are marked *