Site –The sidewalk along Virginia Ave. and the petanque course has been opened to the public. Site work is ongoing at Tract III, retaining ponds have been installed and soil removal will begin in the coming weeks. Additionally, water and storm tie-ins will begin, which will release the start of sidewalks on the west side of Virginia. In the coming months many of the areas on the main site will begin installation of the final hardscapes.
Clubhouse/Lodge – The Clubhouse Post Tension slab has been completed, and the structural steel has also been completed. The structural steel has been completed at the ballroom, as well as the first floor or elevated hollow core concrete. In the coming month, the first topping slab will be poured, and the second floor will be completed structurally.
Pool Building – The glu-lam structure has been completed, and the roof timber has been installed. Protective roofing has been installed, and fire sprinkler has been completed. Going forward in-fill walls will be completed, and storefront windows will be installed. In the coming month, the exterior stonework will begin at the pool building.
Austin Walk I – Infill framing has been completed on the second floor, and structural framing has been completed on the fourth floor. The fifth-floor hollow core slabs have begun installation and will be complete by the end of the month with the topping slab. Next month we will complete another level of structural walls and in the following month roof trusses. Electrical, plumbing, and HVAC will also begin on the third floor.
Austin Walk II – Structural metal studs have been completed in the third floor of the building, and the forth-floor structural hollow core decking has been installed. By the end of the month the fourth-floor structural walls will be completed, and ready for a structural hollow core to be set. Infill framing has been completed on the second floor and will continue along with electrical, mechanical and plumbing rough-in over the coming month.
Austin Walk IV – Footings have been completed, along with all foundation walls and columns. Underground plumbing and electrical have been completed and the first slab on grade pour has been completed. In the coming month, we will complete the slab on grade concrete, and begin forming and pouring the elevated post tension deck.