Site – Underground bio detention Pond C has been completed, and the footings for the wall at detention Pond A have been started. Water meter install has begun, while underground water and sewer onsite continue. Backfill at the Clubhouse retaining wall continues, and excavation for the Austin Walk III building pad will begin next month.
Clubhouse/Lodge – The slab on grade at the loading dock has been poured, and all but shallow footings at the ballroom area of the club house have been completed. Next month footings under the Dining Area and Entry Hall will begin. Following footings, underground electrical and plumbing will begin in these areas.
Pool Building – The remaining retaining walls at the pool building have been poured, and the pool is now ready for deep underground plumbing.
Austin Walk I – Concrete foundations and columns have been completed, and concrete retaining walls will be completed by the end of the month. Next month we will continue to install underground electrical and plumbing, as well as start prep for the parking level slab on grade.
Austin Walk II – Concrete footings are ongoing, and concrete columns have begun. By the end of the month all spread and continuous footings will be complete, and concrete retaining walls will have been started. Underground electrical is ongoing. Next month we will start block walls and complete concrete retaining walls.