The month of November was a busy one at Peachtree Hills Place. The contractor has been installing site utilities and grading the entire month. Most of the underground utilities are in place, and next on the list is the installation of the main detention piping.
The month of December will continue site utilities and grading. The foundations of the building will begin as well. We have started our drilled aggregate piers (deep foundations) in the pool and Community Hall buildings. At a target rate of one pier every 6 minutes, they are installing quite a few piers at a rapid pace. Once these piers are installed in the pool area, we will begin our building footings and foundations.These two trades will be the primary work occurring over the next 6 weeks.
—Brian Thomas, Vice President of Construction