Site – The Pond A wall is complete, and the crews have moved on to begin site walls at Terraces, and the Club House. Water meter install is complete, while underground water and sewer onsite
continue. Excavation of Austin Walk III has begun, and the grading at the road leading to the Phase 1 houses is complete to curbing. Next month we will begin paving, and finish backfill at the clubhouse.
Clubhouse/Lodge – The first elevated slab has been poured at the clubhouse at the exercise room. Footings under the administration offices has begun, and backfill at the ballroom has started. Underground electrical and plumbing are ongoing in all these areas. Next month we will pour the slab on grade at the ballroom, and begin forming the elevated deck at dining.
Pool Building – Deep underground plumbing has been completed, and shallow plumbing and electrical has been done. Prep for the slab on grade has begun, and will be poured after the retaining walls at the Clubhouse have been completed. Next month we will begin layout for the glulam structure.
Austin Walk I – All concrete retaining walls have been completed, and the parking slab on grade have been completed. The first elevated slab has begun forming, and electric and plumbing rough in is complete in 50% of the slab. Forming of the second half of the elevated slab will begin after rebar and PT cables are in place in the first half. Next month we will pour our first PT deck, and begin structural steel.
Austin Walk II – All spread and continuous footing have been completed, columns above these foots have also been completed. Block walls to grade have been completed, and slab on grade prep has begun. Underground electrical and plumbing is ongoing. Next month we will pour the slab on grade at parking, and begin forming the elevated deck.